Update 11/30/2015 - Eddie

  • I've applied to several jobs now, but need to do more.
  • Working on rewrites for paper. Plan on finishing it by the end of this week.
  • MHD version of 3D pulsed jets was having some restart issues, but I fixed it. Below is an image from a run with an initially purely toroidal field with beta = 1, with 64 cells per jet radius. This run (6 out of 120 frames) took 3 hours on 576 cores. The current standard output estimates that the run will take about 3 weeks to finish. Perhaps it's a better idea to do a longer run at a lower resolution (32 cells per jet radius) before continuing with this production-level run. I just don't want to waste time and resources if there turns out to be some difficult-to-explain-weirdness in the jet at later times.